Drop-off Zone construction at Grace Primary School

Published by Admin on

Drop-Off Zone Construction At Grace Primary School


Date

Location

Total Value

Consulting Engineers

May to June 2016

Pinelands, Western Cape

R 410 000

Oikos Consulting – Gavin Graham | Tel: 072 674 8738



Description of services

1| Remove 1.0m deep unsuitable material from future building footprint to form berms for landscaping.

2| Fill with imported sand and compact in 150mm layers.

3| Construct 2.5m parallel drop off zone with barrier kerbing, 150mm base and 35mm asphalt surfacing.

Categories: Portfolio